Aug 23, 2019Section 27-2013 adm code paint with light colored paint to the satisfaction of this department the ceiling and all walls in the kitchen located at apt 3b, 3rd story, 1st apartment from south at westNov sent out
Aug 23, 2019Section 27-2013 adm code paint with light colored paint to the satisfaction of this department the ceiling and all walls in the bathroom located at apt 3b, 3rd story, 1st apartment from south at westNov sent out
Aug 23, 2019Section 27-2013 adm code paint with light colored paint to the satisfaction of this department the ceiling and all walls in the foyer located at apt 3b, 3rd story, 1st apartment from south at westNov sent out
Mar 25, 2019Section 27-2005 adm code refit all windows throughout in the entire apartment located at apt 6d, 6th story, 1st apartment from south at westNov sent out